Sprint Nextel releases new 2GHz BAS table

Sprint Nextel released a new table Sept. 14 showing the progress of the 2GHz Broadcast Auxiliary Service relocation project.

The table updates figures submitted to the FCC when the company along with the National Association of Broadcasters (NAB), Association for Maximum Service Television (MSTV) and Society of Broadcast Engineers (SBE) petitioned the commission for a 29-month extension of its Sept. 7 deadline for completion of the project.

As of Sept. 14:

Phase March 2007 Sept. 2007 Percentage Increase Since March 2007
Markets kicked off by Sprint Nextel 100% 100% Complete
BAS stations engaged in transition 100% 100% Complete
Inventories submitted by broadcasters 99% 100% Complete
Inventories verified and agreed by Sprint Nextel 80% 99% +24%
Quote packages submitted by broadcasters 37% 66% +78%
Quote packages approved by Sprint Nextel 30% 61% +103%
Frequency relocation agreements signed 22% 48% +118%
Purchase orders submitted by broadcasters 17% 41% +141%
Purchase orders fulfilled by manufacturers 5% 15% +200%
Equipment installed 2% 8% +300%


Comments
Post New Comment
If you are already a member, or would like to receive email alerts as new comments are
made, please login or register.

Enter the code shown above:

(Note: If you cannot read the numbers in the above
image, reload the page to generate a new one.)

No Comments Found




Friday 3:00PM
Google Debuts Android TV
“We’re simply giving TV the same level of attention that phones and tablets have traditionally enjoyed.” ~ David Burke, Google


 
Featured Articles
Discover TV Technology